Design Flexibility in ORE Development/Consenting and Planning
Bohan, Greg ; Dunne, Jeannine ; Kelly, Aoife
Bohan, Greg
Dunne, Jeannine
Kelly, Aoife
Citations
Altmetric:
Date
2024-11-01
Publisher
Marine Institute
Collections
Research Projects
Organizational Units
Journal Issue
Abstract
When developing an offshore wind farm, between initial project scoping, the submission of a planning
application, and construction, there will be several iterations of project design as more detailed
information is gathered on the site, as technology advances, and as engagement with the supply chain
increases and suitable components and suppliers are identified. As project development progresses,
however, projects will be required to prepare and submit their planning applications. Final design
parameters will not be available at the time of application submission due to the long lead times
between the preparation and submission of a planning application and the eventual construction of
an offshore wind farm, as well as the phased nature of site investigation and design strategies
employed by projects. Projects will therefore require flexibility in their consented design envelope, to
account for details that are not finalised at the time of planning application submission. This report makes recommendat
Description
Funder
Citation
Bohan, G., Dunne, J. & Kelly, A. (2024). Design Flexibility in ORE Development/Consenting and Planning. Marine Research Programme 2021-2027. Marine Institute, Ireland